January 2008 - Issuance of revised Master Use Permit by the City of Seattle
April 2008 - Demolition of administrative building will commence
June 2008 - Completion of demolition
August 2008 - Repair of Sanctuary building and upgrades will commence
March 2009 - Shoring & Excavation will commence
March 2010 - Construction of High Rise portion of project will commence
July 2011 - Completion of Office Building and tenant move-in