Construction Schedule

    January 2008 - Issuance of revised Master Use Permit by the City of Seattle
    April 2008 - Demolition of administrative building will commence
    June 2008 - Excavation will commence on the site
    August 2008 - Construction of underground parking facility will commence
    July 2009 - Construction of High Rise portion of project will commence
    July 2010 - Completion of Office Building and tenant move-in